Project Overview New Facilities Renovations or Improvements
The Soccer Complex located on Wire Road will be expanded to include additional fields as well as the addition of a 56,000 square foot enclosed soccer/multipurpose complex that can be converted into smaller multi-use spaces and courts for a wide range of recreational programming. Additional features will include a family pavilion with restrooms, pedestrian trails, an additional restroom on the south end of the park, expanded parking, and picnic shelters to serve as team assembly areas or family picnic sites. Entrance to the soccer complex will include a roundabout for improved access and through traffic. The project is part of the City of Auburn's Parks‚ Recreation‚ & Culture Master Plan.
The project was completed on Jan 9, 2024 with a total capital budget of $11,468,097.03.
Photos




Timeline
Construction Finishes
Jan 9, 2024
Construction Starts
Feb 21, 2022
Contracts Finishes
Feb 16, 2022
City Council Starts
Jan 18, 2022
Contracts Starts
Jan 18, 2022
Bid Opening Starts
Jan 6, 2022
Bid advertisement Finishes
Nov 30, 2021
Bid advertisement Starts
Nov 14, 2021
Design Finishes
Nov 1, 2021
Design Starts
Dec 23, 2019
Council Starts
Nov 19, 2019
Consultant Selection Finishes
Feb 2, 2019
Consultant Selection Starts
Nov 5, 2018
RFP for Design Finishes
Oct 26, 2018
RFP for Design Starts
Oct 1, 2018