Jan Dempsey Renovation
Development Services Building
171 N Ross St
-
(334) 501-7390 -
webengineering@auburnalabama.org -
- M-F
- 7:30AM-4:30PM
-
\t\t\t\t{{SocialMediaLinks}} \t\t\t \t\t
Project Overview New Facilities Renovations or Improvements
The Jan Dempsey Community Arts Center will receive an expansion of approximately 8,000 square-feet to accommodate classes for diverse dance disciplines as well as the Dean Road Ceramics Studio by providing needed studio, classroom, and gallery space. The interior of the existing building, including the dressing room, storage area, and office will be reconfigured. Improvements to the existing building will include renovating the restrooms, doorways, kitchen, dressing room, and main entrance. A new sidewalk will be constructed along the front of the facility. Additional parking will be constructed along East Drake Avenue, the existing building will receive roof repairs and roller shades will be installed. Relocating the ceramics studio to the Jan Dempsey Community Arts Center will free up space at Dean Road for therapeutics programs, as well as social and recreational activities designed for special needs residents. The project is part of the City of Auburn's Parks‚ Recreation‚ & Culture Master Plan.
The project was completed on Mar 27, 2024 with a total capital budget of $5,182,735.71.
Jan Dempsey Community Art Center plaque ceremony set for March 27th, 2024.
Photos
Timeline
Construction Finishes
Mar 27, 2024
Construction Starts
Jan 9, 2023
Contracts Finishes
Dec 23, 2022
Contracts Starts
Nov 16, 2022
City Council Starts
Nov 15, 2022
Bid Opening Starts
Oct 4, 2022
Bid advertisement Finishes
Sep 29, 2022
Bid advertisement Starts
Sep 11, 2022
Design Finishes
Oct 1, 2021
Design Starts
Dec 23, 2019
Council Starts
Nov 19, 2019
Consultant Selection Finishes
Feb 2, 2019
Consultant Selection Starts
Nov 5, 2018
RFP for Design Finishes
Oct 26, 2018
RFP for Design Starts
Oct 1, 2018