Environmental Services & Public Works Complex Relocation

Development Services Building
171 N Ross St
-
(334) 501-7390 -
webengineering@auburnalabama.org -
- M-F
- 7:30AM-4:30PM
-
\t\t\t\t{{SocialMediaLinks}} \t\t\t \t\t
Project Overview New Facilities Renovations or Improvements
The City’s Public Works and Environmental Services departments will relocate to Wire Road to enhance mobilization, operation and the efficiency of the City’s delivery of public services within a growing community. The new campus will include facilities for current and future equipment as well as materials storage for Public Works, Traffic Engineering and Environmental Services, which includes garbage, trash, recycling, animal control and fleet services. Fleet Services is responsible for maintaining all of the City’s vehicles and motorized equipment.
The project was completed on Jan 16, 2024 with a total capital budget of $33,823,931.96.
Photos




Timeline
Construction Finishes
Jan 16, 2024
Construction Starts
Jun 1, 2022
Contracts Finishes
May 16, 2022
Contracts Starts
Apr 20, 2022
City Council Starts
Apr 19, 2022
Bid advertisement Finishes
Apr 5, 2022
Bid Opening Starts
Apr 5, 2022
Bid advertisement Starts
Jan 22, 2022
Design Finishes
Aug 1, 2021
Design Starts
Oct 5, 2020