North Dean Road & East University Drive Intersection Improvements

Development Services Building
171 N Ross St
-
(334) 501-7390 -
webengineering@auburnalabama.org -
- M-F
- 7:30AM-4:30PM
-
\t\t\t\t{{SocialMediaLinks}} \t\t\t \t\t
Project Overview Traffic Transportation & Parking Improvements
This project consists of installing dual left turn lanes on North Dean Road at its intersection with East University Drive to accommodate westbound and eastbound turn movements. Removal of the existing traffic signal and installation of a new 4-pole/mast arm signal is also included in this project. The roadways will be resurfaced entirely within the construction limits. The project is part of the City of Auburn's Comprehensive City-Wide Traffic Study.
Please note that project completion dates are subject to change based on weather and other conditions. Project anticipated finish dates may not coincide with actual day of opening.
North Dean Road, East University Drive striping expected April 16-22
Status
- Design
- Bid Advertisement
- Contracts
- Construction
100%
The contractor has completed striping and the project is nearing completion with only the punch list remaining.
Photos




Timeline
Close Out Finishes
Jun 1, 2025
Close Out Starts
May 3, 2025
Construction Finishes
May 2, 2025
Construction Starts
Jun 20, 2024
Contracts Finishes
Jun 19, 2024
City Council / AWWB Starts
May 21, 2024
Contracts Starts
May 21, 2024
Bid Opening Starts
May 7, 2024
Bid Advertisement Finishes
May 7, 2024
Bid Advertisement Starts
Apr 14, 2024
Design Finishes
Jun 30, 2023
Design Starts
Sep 5, 2022